As detailed below, and subject to approval of the City Council and the Mayor, the Taylor Yard G2 Projects will be designed and constructed over an approximately 10-year period:
2017
City of Los Angeles purchased the Taylor Yard G2 parcel
Bureau of Engineering selected consultant team to develop Taylor Yard River Park Project
2018
Initial public meetings held to solicit input on project ideas
Preliminary design concepts developed
2019
Site assessments completion
Response Plan development
Implementation Plan/Preliminary Design Report completion
Begin environmental review and documentation
2020
Habitat Viewing Platform Project opens
2021
Taylor Yard Pedestrian and Bicycle Bridge opens
Vista del Rio Project opens
2024
Water Quality and Initial Park Improvements Project opens
2028
River Park Project opens