Groundwater Sampling
22 samples from 16 monitoring wells
Soil Gas Sampling
228 sample locations
452 total samples
Soil Sampling
78 locations
645 total samples
Site Assessment Milestones
2018
January: Engineering submits Site Assessment Work Plan to DTSC
March: DTSC approves Site Assessment Work Plan
April: Engineering publishes Press Release—Site Assessment work beginning/geophysical survey begins
May: Fact sheet including a Project Schedule with site testing information posted to tayloryardg2.com
June: DTSC publishes public work notice—soil and soil gas sampling begins
September: All sampling activities complete
October: Lab results complete
November: Draft Report of Findings Submitted to DTSC
December: DTSC review of Draft Report of Findings
2019
February: DTSC comments on Draft Report of Findings was submitted to Engineering
May: Site Assessment results presented to the public
June: Final Report of Findings submitted to DTSC
Upcoming
DTSC to review and approve Response Plan
Cleanup begins