Details on Site Sampling and Testing

Groundwater Sampling

22 samples from 16 monitoring wells

 

Soil Gas Sampling

228 sample locations

452 total samples

 

Soil Sampling

78 locations

645 total samples

 

Site Assessment Milestones

2018

January: Engineering submits Site Assessment Work Plan to DTSC

March: DTSC approves Site Assessment Work Plan

April: Engineering publishes Press Release—Site Assessment work beginning/geophysical survey begins

May: Fact sheet including a Project Schedule with site testing information posted to tayloryardg2.com

June: DTSC publishes public work notice—soil and soil gas sampling begins

September: All sampling activities complete

October: Lab results complete

November: Draft Report of Findings Submitted to DTSC

December: DTSC review of Draft Report of Findings

 

2019

February: DTSC comments on Draft Report of Findings was submitted to Engineering

May: Site Assessment results presented to the public

June: Final Report of Findings submitted to DTSC

 

Upcoming

DTSC to review and approve Response Plan

Cleanup begins